Overview
Treatment Plant History
Construction of the first public system of sanitary sewers and
of the treatment plant began in 1966 and was designed to be expandable
to meet the growth of the Town of Billerica population, which
was estimated to be 50,000 by the year 2000. The original Wastewater
Treatment Facility was designed to treat 0.8 MGD (million gallons
per day), by using aeration tanks and final settling tanks followed
by chlorination before discharge into the Concord River.
In 1975 the first upgrade took place, which doubled the aeration
tank capacity, added an additional final settling tank and added
a sludge disposal building which housed a coil vacuum filter
for sludge thickening. This upgrade brought the plant capacity
to 1.6 MGD.
In 1982, a return sludge building was added to house the sludge
return pumps, which had been externally mounted on the final
settling tanks.
In 1984, the Town of Billerica landfill was closed which was
where the thickened sludge was disposed of. We began hauling
liquid sludge by tanker truck to Greater Lawrence and then to
Upper Blackstone Abatement Facility.
In 1988, construction began on the next expansion, which would
bring the Wastewater Treatment Facility to its present capacity
of 5.5 MGD.
The Latest Upgrade
The new facilities include: preliminary treatment (mechanically
cleaned bar screens and grit removal equipment); primary treatment
(three 60' diameter primary settling tanks, primary sludge
pumps, primary scum pumps, primary sludge holding tank);
replacement
of the mechanical aerators in the aeration tanks with a diffused
aeration system; three 60' diameter final settling tanks; three
recalculated sludge pumps; secondary scum pump; new chlorination
equipment; post-aeration facilities; plant water system improvements;
blended sludge holding tank; sludge transfer pumps; new dissolved
air flotation thickener; two 2 meter belt filter presses; associated
polymer storage, transfer and conditioning equipment; sludge
conveyors; composting facility and storage areas; and a new
administration and maintenance building which houses the
Plant Superintendent's
office, control room, laboratory, personnel facilities, aeration
blowers, maintenance shop, garage and emergency generator.
Composting Success
Composting started in Billerica in August
of 1990 after the plant upgrade had been completed. However,
in March of 1992,
odor problems
and complaints forced the composting operation to come
to a halt. Liquid sludge had to be hauled (at $.03 cents
a gallon)
to the
Upper Blackstone Wastewater Treatment Facility (WWTF),
which had to be treated and incinerated (at $250.00 per dry
ton).
All of these additional costs added up to $175,000.00 for
the
year.
In addition to all of this, the surrounding neighborhoods
had formed an Odor Control Committee and were very vocal at
Town Meeting. They were able to generate local newspaper
interest
in their story and this caused the shutdown of the composting
operation.
In the fall of 1992, the Town of Billerica WWTF started experimenting
with wood ash as a bulking agent instead of wood chips (which
has been used in the original start up). With cooperation of
the Odor Control Committee, the WWTF started composting at 50%
capacity to show the plant could eliminate odors with a change
in the bulking agent. By February of 1993, odor control had been
successful and the WWTF started composting at 100% capacity.
The WWTF has generated between 6,000 and 8,000 cubic yards of
Type I Compost per year since 1993, due to the inception and
use of wood ash and sawdust as a bulking agent.
In May of 1997,
the Town of Billerica Wastewater Treatment Facility submitted
an application to the EPA for the "Beneficial
Use of Biosolids Award". This is a ten year old program
that recognizes the outstanding efforts to promote the beneficial
use of biosolids. The Billerica WWTF won third place and became
the only Massachusetts facility to win a National Beneficial
Biosolids Award in the history of the program. The award was
officially received October 20, 1997 at the EPA Wastewater Management
Excellence Ceremony in Chicago by the former Superintendent of
the Billerica Wastewater Treatment Facility, Arthur Malcuit.
|
|
Office Address:
70 Letchworth Ave.
Billerica, MA 01862
Phone: (978) 671-0956
Fax: (978) 671-1305
|
Office Hours:
Monday - Friday
7:30am - 3:30pm
|
|