Billerica Water Works Overview
Billerica Water Works was established by an act of the
Massachusetts Legislature in 1897. Construction of the original
works began in 1898 and continued for several years. The water
works was first activated in January of 1899. Water was at that
time drawn from wells located in the area of the present Water
Treatment Plant, where the original pumping station building
remains.
Treatment Plant
The Water Treatment Plant (WTP) was built in 1955. As originally
built it had a capacity of 3.5 million gallons per day (MGD)
and was intended to be expanded to 7 MGD at a later time.
In 1967 the plant was expanded to its intended maximum capacity.
As growth in Town continued the plant's capacity was again
increased in 1976, this time to 14 MGD.
Over the years some of the process have changed.
1) In the 1979 the Powdered Activated Carbon applied in the
pretreatment was replaced by changing the filter media from
anthracite coal to Granular Activated Carbon this lowered cost
and reduced sludge volume.
2) In the 1987 sodium hydroxide was replaced with potassium
hydroxide to reduce the sodium level in the water.
3) In December of 1992 fluoridation of the Water Supply began.
4) In May of 1997 an ozone generating and feed system was
installed. This was done to remove the manganese which caused "brown
water". This treatment also reduces taste and odors and
very effectively inactivates virus and cysts.
5) In September of 1999 ammonia was added to change the secondary
disinfectant to from free chlorine to chloramines. This was
done to lower the trihalomethanes levels. This adjustment has
been very successful.
Treatment Plant Operations
The Water Treatment Plant is designed as a continuous process,
therefore it runs on a twenty four hours a day seven days
a week basis. The Treatment Plant is normally shut down only
for maintenance, severe storms, and power failures.
The Filter Operators monitor the process by checking chemical
use every hour and bench testing water from various parts of
the treatment process every other hour. The Filter Operators
also receive bulk chemical deliveries. Daily chemical handling
involves transferring of chemical from storage to day tanks.
The operators also perform maintenance on the some of the control
systems as needed. They adjust the treatment rate according
to changes in the standpipe water level, which is a reflection
of water consumption by our customers.
The laboratory staff performs the equipment calibrations and
non-daily testing. Most critical of these are the bacterial
samples collected and analyzed each week from ten DEP approved
site in the distribution system. The laboratory staff also
collects the many samples required to comply with the Safe
Drinking Water Act. and writes the annual Consumer Confidence
Report.
Distribution Works
The Distribution Works consist of the piping that carries
the water to the customers, this piping ranges in size
from 2" to
24" diameter. The original mains most of which are still
in use are made of pit cast iron. Shortly after the original
construction galvanized iron piping came into use, usually
only for one and a half to two inch lines, some of these
are still in service. In the mid-1950s cement asbestos was
used for water mains. The current material used is ductile
iron.
There are over 2000 fire hydrants connected to our system,
of these over 1800 are public hydrants under the care of our
staff. The hydrant inventory by age is given below:
No date, includes unknown date ..........
13.9%
1956 - 1959 ...................................... 1.46%
1960 - 1969 ...................................... 19.75%
1970 - 1979 ...................................... 20.48%
1980 - 1989 ...................................... 21.12%
1990 - 1999 ...................................... 23.26%
Note: Hydrant manufacturers did not begin casting the year
in the hydrant barrels until the mid 1950s
Service lines are the connections from the main to the customers
water meter or fire system. The older lines are galvanized
iron tubes. Since the 1950s copper has been used for the smaller
house lines. Fire lines are normally of the same materials
being used for water mains.
The two tanks in the Center are called standpipes. They are
connected to the Treatment Plant by a sixteen and a twenty-four
inch diameter Forced Mains. These Forced Mains also diffuse
water to the distribution works. The function of the standpipes
are to even out the production demand on the treatment plant,
maintain pressure, and to have on hand a ready supply of water
for emergencies. Each standpipe has only one connection to
the distribution system, they "float" on the system.
When the treatment plant is producing more water than is being
consumed the water level in the standpipes rises. When there
is more demand than production the water level in the standpipes
falls. The water level in the standpipes is normally kept within
fifteen feet of the overflow. Water pressure at any particular
point in town is controlled by the distance that particular
point is below the water level in the standpipes.
Distribution Works Operations
Our system averages about forty main breaks per year. Most
of these occur in the winter. Sometimes the pipe is found
to have a rock under the pipe or be passing through an old
sewer trench which has settled. The majority of breaks are
unexplained. When a main fails we must isolate (shut-off)
the area and call Dig Safe to locate underground utilities.
There are two basic types of main breaks. The first is beam
breakage, which results in the pipe splitting around its circumference.
We repair this with a "wrap-around" clamp. The second
type of break is lengthwise. This is usually more difficult
to repair and can require a larger excavation. A lengthwise
break requires that a section of pipe be cut out and replaced,
these cracks can run nine to ten feet along the pipe. After
the break has been repaired and the excavation has been largely
filled in the water will slowly be turned on to fill the main.
Then the area mains will be flushed through the hydrants to
rid the main of air and sediment.
The flushing of the hydrants are usually done twice a year.
Although it appears to be a hydrant based activity its purpose
is to flush sedimentation from the water mains, this is normally
done by opening all the hydrants at the ends of the mains.
This usually takes two to three weeks.
Our staff performs the maintenance and replacement of public
hydrants. All of our hydrants have automatic drains, which
drain the barrel after use to prevent freezing and the accumulation
of stagnant water. Occasionally these do not work and require
repair. Because we use a river source there is great seasonal
fluctuations in the water temperature. This does occasionally
cause hydrants to leak. The majority of hydrant replacements
are done by our staff. The exceptions are those cases where
hydrants are damaged by vehicle collisions. These are replaced
by a contractor at the expense of the driver's insurance company.
Most of our hydrants have stainless steel identification tags,
which give the hydrant's inventory number. Our staff also paints
the public hydrants as weather permits. Painting is an on going
and continuous operation.
Our staff repairs or replaces the portion of the service lines
between the main and the property line as needed. These are
similar to water main repairs. Many of these are not emergencies
but are scheduled. When an old galvanized iron service line
corrodes the inside opening becomes smaller which restricts
the flow, replacing these restores capacity. We usually will
do this after the homeowner has changed the service line on
his or her property to type K copper.
As other utilities mark out the location of their buried lines
when we are digging we must locate our lines for them. We are
not a member of the Dig Safe System, and must be contacted
separately by those are planning to excavate. We also mark
out our lines at the planning stage of projects such as the
sewer collection system extensions.
Cross Connection Control Program
The function of this program is to see that connections between
the drinking water system and any other liquid or gas do
not pose a threat to the safety of the drinking water. There
are two conditions under which cross connections are a problem.
The first is when the pressure in the main drops and contaminates
are siphoned back into the mains. This can happen when there
is a main break or a large fire demand in the area. The second
is when the pressure a building's plumbing system exceeds
the pressure in the main. This can be caused by pressure
type boilers or any process which is connected to the plumbing
and heats liquids or gases. Billerica Water Works has regulations
requiring that all commercial building have a reduced pressure
zone (RPZ) valve after the water meter. While our efforts
are directed to the commercial properties the homeowner should
be aware that he or she may have cross connections in their
plumbing. The most common is probably at garden hose with
a sprayer attached or a hose being placed in swimming pools.
Cross Connection Control Program Operations
The Head Tester is responsible for surveying all commercial
building for cross connections. When these are found and
cannot be physically separated a special check valves must
be installed. Normally a RPZ valve will be used. The exceptions
are the valve on the fire lines which are double checks.
The Head Tester tests the RPZ valve twice a year and the
double checks once a year. The Head Tester also inspects
and seal primary meters in new buildings.
|
|
Office Address:
270 Treble Cove Road
Billerica, MA 01862
Phone: (978) 671-0957
Fax: (978) 671-0911
|
Office Hours:
Monday - Friday
7:30am - 3:00pm
|
|